MAIN DEVELOPMENT ACHIEVEMENT

What You Need To Know

Block A-18 Gas Field is located offshore in the lower part of the Gulf of Thailand approximately 150 km Northeast to Kota Bharu and 160 km East of Narathiwat in water-depth of about 60 meters in contract area of Block A-18 in the Joint Development Area. Block A-18 field development project consists of 12 wellhead platforms (CKA, CKB, CKC, CKD, BLC, BLB, BLC, BMA, BMB, BMD, SYA and SYB), Central Processing Platform & Living Quarters (CKP), Riser Platform (CKR) and FSO (Puteri Cakerawala). Committed processed gas at a rate of 790 mmscf/d is delivered to the Buyers' sales pipeline through delivery point located on the riser platform. The field is developed with the following facilities (as shown in pictures below):

Muda, Jengka, Tapi, Amarit, Melati, Andalas and Tanjung Fields are located offshore in the Gulf of Thailand approximately 150 km northeast to Kota Bharu, 250 km east of Songkhla province and 350 km north of Kemaman Supply Base (KSB) in water depth of ranging between 55-65 meters in contract area of Block B-17 & C-19 in the Joint Development Area.

As of year end 2018, The field development project consists of thirteen (13) wellhead platforms (Block B-17 &C-19: MDA, MDB, MDC, MDD, MDE, MDF, JKA, JKB, TPA and AMA and Block B-17-01: MTA, ADA and TJA), Muda Central Processing Platform (MDPP), Living Quarter Platform (MDLQ), Flare Tripod and Floating Storage Offloading (Ratu Sonkhla FSO). Processed gas with DCQ of 335 mmscfd will be delivered for a period of 10 years and 250 mmscfd for remaining 6 years, which will end on 1st January 2026. The fields are developed with the following facilities as shown in the picture below.

January First gas from Cakerawala

First gas from Cakerawala field through CKA and CKB was achieved

May First gas from Bumi

First gas from Bumi field through BMA was achieved

December First gas from Bulan

First gas from Bulan field through BLA was achieved

September First gas from Suriya

First gas from Suriya field through SYA was achieved

May First gas from SYB

First gas from SYB was achieved

March First gas from BMB

First gas from BMB was achieved

October CKX

CKX (Booster Compression Project) fabrication commenced

November First gas from BLB

First gas from BLB was achieved

June First gas from BMD

First gas from BMD was achieved

February First gas from BLC

First gas from BLC was achieved

July CKX

CKX installation was completed

September First gas from CKX

First gas from CKX was achieved

February First gas from Block B-17&C-19

First gas from Block B-17&C-19 commenced in February 2010 through Phase I consisting of MDA, MDB, MDC, MDD and JKA

First gas from Phase II

First gas from Phase II consisting of MDE and JKB was achieved

April First gas to TTM EVA

First gas to TTM EVA pipeline was achieved

November Installation of Phase III

Installation of Phase III development platforms consisting of TPA, MDF and AMA was completed

February First gas of Phase III

First gas of Phase III is expected

March First gas from Block B-17-01

First gas from Block B-17-01 through commissioning of MTA platform

March First gas from Phase IV

First gas from Phase IV consisting of ADA, TJA and ADB